Question #: 30
Topic #: 1
[All RCDD Questions]

An RFQ usually provides more detail than RFP in selecting material such as

  • A. delivery date.
  • B. mounting option.
  • C. make.
  • D. color.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Sameer205
2 weeks ago
Selected Answer: C
An RFQ (Request for Quotation) and an RFP (Request for Proposal) serve different purposes: RFP (Request for Proposal): Focuses on how a vendor will meet the project’s needs. It asks for design, methodology, and technical approach — more conceptual and performance-based. RFQ (Request for Quotation): Focuses on what exactly is being purchased. It provides specific material details, including: Manufacturer (make) Model number Quantity Color, finish, mounting options, delivery dates, etc. So while the RFQ may also include details like color or mounting options, the key distinguishing detail — the one that represents more specificity about the actual product — is the make.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other