Near the end of a Sprint, the team realizes that they will not be able to complete the stories they had committed to.
What is the best course of action for the team?

  • A. Add resources and team members to meet the goals of the current Sprint.
  • B. Ask the Product Owner to decide which stories can be delayed until the next Sprint.
  • C. Decide on a new definition of 'done' for the Sprint Backlog Items.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
5e90ca0
1 month, 1 week ago
Selected Answer: B
B. Ask the Product Owner to decide which stories can be delayed until the next Sprint. In Scrum, scope flexibility is allowed within a Sprint if the team realizes they cannot complete all committed items. The Product Owner is responsible for prioritizing the Product Backlog and deciding which items deliver the most value.
upvoted 1 times
...
5e90ca0
1 month, 3 weeks ago
Selected Answer: B
Adding resources (A) or changing the Definition of Done (C) violates Agile principles and can lead to technical debt or team burnout. Scrum encourages empirical decision-making and collaboration with the Product Owner to manage scope responsibly.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...