A Scrum Team works on a project in 2-week Sprints. During the Sprint Planning meeting of the third Sprint, the Product Owner says:
“I will be going on holiday in 2 weeks. Let’s change the duration of this Sprint to 4 weeks, so that I will be back when it ends.”
Should the duration of the sprint be increased?