Exam PRINCE2-Foundation topic 1 question 430 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 430
Topic #: 1
[All PRINCE2-Foundation Questions]

What is a risk actionee responsible for?

  • A. Identifying risks to the project that might occur in their department
  • B. Owning and authorizing the use of the risk budget to fund risk responses
  • C. Managing, monitoring and controlling of all aspects of an assigned risk
  • D. Carrying out a risk response action to respond to a particular risk
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
7afc58d
3 weeks, 4 days ago
Selected Answer: C
The person who is the nominated owner of agreed actions to respond to a risk. This role is also known as the risk actionee.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...