If burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate?

  • A. The evolution of the cost spent on the project.
  • B. When all work will be completed to the Scrum Team can be released for other work.
  • C. When the work remaining will likely be completed if nothing changes on the Product Backlog or the Development Team.
  • D. When the project will be over if the Product Owner removes work that is equal in effort to any new work that is added.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Reference:
https://www.knowledgehut.com/tutorials/scrum-tutorial/sprint-burndown-chart

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
giver
2 weeks, 1 day ago
Selected Answer: C
A release burndown chart in Scrum: Shows work remaining versus time for a release. The trend line projects the expected completion date based on current velocity. It assumes no major changes in scope, team capacity, or work complexity.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...